OSET WATER

TREATMENT PLANT

Project: New Water Treatment Plant Completion

Date: 2008 

Cost: $600 million NOK (approx. $67 million USD)

Design 

• Capacity: 390,000 m3/day

• Provide drinking water to 85% of population of Oslo

• Construction: Two 750 m long, 28 m wide and 76 m high cavern halls

WIGGINS ISLAND COAL 

EXPORT TERMINAL

Project: New Export Terminal Completion

Date: 2015 

Cost: $3.3 billion USD 

Design 

• Capacity: 27 million tonnes per annum (mtpa)

• A rail receival facility designed to handle a maximum throughput of 8,250 tons per hour(@ 900 kg/m3)

• 5.6 km long overland conveyor

• Stockyard capacity: 7.85 million tons of coal

• Materials handling and sampling systems feeding the 2km long jetty conveyor

• Single berth with a travelling ship loader to fill ships at 8,250 tonnes per hour

• Channels and wharf to accept a range of vessels from 40,000dwt to 220,000dwt

• 732 kV substation, access roads, workshops, administration offices and amenities

MARINE TERMINALS

Many of our large projects include a marine terminal for Import/Export purposes. 

Examples: 

• LNG

o CNL Quintero (Chile)

o Peru LNG (Peru)

o Isle of Crain LNG (UK)

o Golden Pass LNG (USA)

• Mining

o Goro Nickel (New Caledonia)

o Koniambo Nickel (New Caledonia)


PLUTO LNG

Project: Pluto LNG 

Date: 2008-2009, 2015

Works Include: EPC project Bulk storage tanks, LPG spheres, Offshore Platform, Onshore Gas Train 1 & 2 FW 

Maersk PEREGRINO FPSO

Project: FPSO 

Date: 2009

Works Include: Systems Completion &

Turnover/handover (RFO), Commissioning advisor 


PEARL GTL

Project:  Integrated gas and gas-to-liquids project

Date: 2009

Works Include: Systems Completion & Turnover/Handover (RFO), Commissioning advisor


Read Article Here

NORTH RAKIN

RE-DEVELOPMENT PROJECT

Project: FPSO 

Date: 2010

Works Include: Inspection Services, Systems Completion & Turnover/Handover (RFO), Commissioning, Certification


BRIDGEWATER

HYDROELECTRIC STATION

Project:  Hydroelectric Power Station

Date: 2010

Works Include: Systems Completion, Certification &

Turnover/Handover (RFO), Preservation

VOGTLE NUCLEAR UNIT 3 & 4

Project: New Build AP700 Nuclear Power Plant 

Date: 2014

Works Include: Systems Completion, Certification &

Turnover/Handover (RFO), Preservation - Start-up


JOHN W. TURK JR.

POWER PLANT

Project:  New Build 650 MW Ultra super critical Plant

Date: 2007

Works Include: Systems Completion, Certification &

Turnover/Handover (RFO), Preservation

JIMBLEBAR PROJECT

Project: Open-Cut Pit Iron Ore Mine

Date: 2013

Works Include: Inspection Services, Systems Completion

& Turnover/Handover (RFO), Commissioning, Certification


OYU TOLGOI PROJECT

Project:  One of the Largest Copper and Cold Mine

Date: 2010

Works Include: Systems Completion, Certification &

Turnover/Handover (RFO), Preservation

MA'ADEN ALUMINUM

PROJECT

Project: Mine

Date: 2010

Works Include: Systems Completion, Certification &

Turnover/Handover (RFO), Preservation


quotesArtboard 1 copy 2

Working with Complan has been a game-changer for our business. Their team was able to quickly understand our project requirements and provide customized solutions that helped us streamline our processes and improve our overall efficiency.

C. Lang

Project Execution Consultant

Interested in our services? We’re here to help!

We want to know your needs exactly so that we can provide the perfect solution. Let us know what you want and we’ll do our best to help.

Contact Us Today
Share by: